Battery energy storage has a critical role to play in enabling the UK’s future energy system

The UK has made significant progress towards a low carbon electricity system, with wind and solar energy now accounting for one third of electricity generation. However, where previously coal-fired power plants were turned up and down to balance the network – matching electricity supply with demand – wind and solar generation is weather dependent. This presents significant challenges for network operators. 

Battery storage will provide much of this network balancing role  in the UK’s transition to a renewable energy powered electricity network. With wind and solar generation fluctuating across the day, batteries will store energy when there’s more than needed to meet demand and discharge it when there’s  less than needed.  

Aside from network balancing, battery storage also provides other fundamental ‘healthy network’ features such as grid stability. Where in the event that a major power source, such as a wind farm, goes offline, power from batteries can be  deployed instantly to re-balance  the network.

Securing cleaner, lower cost energy in the short-term

a renewable future

Supporting the longer term transition to zero emissions transport and heat

The next 25 years will see electricity demand double as our petrol cars and gas-fired heating systems are replaced by electric versions to achieve the UK’s target of reducing carbon emissions to zero by 2050.

Battery storage will minimise the costs of this transition by reducing the number of new solar and wind projects required to meet this increased peak demand for electricity and the level of investment in strengthening the UK transmission network to transport energy from offshore wind farms to UK homes.

battery storage explained

What is a battery energy storage system, and how do you build one?

We call our battery projects Energy Hubs as the energy they store ensures that supply and demand are constantly balanced. The basic building blocks of an Energy Hub are the same well-known Lithium-Ion batteries found in everything from cordless vacuum cleaners to electric vehicles . These individual battery cells are connected together to form larger units that are housed in individual containers.

Each one of those containers is a 3 metre cube that can power 1,500 homes for one hour.  Each container is connected via an inverter – to convert the electricity from direct to alternating current – to a substation on the site, which acts as the interface between the project and the electricity distribution grid. 

Almost everything is manufactured offsite to reduce construction times and disruption. The prefabricated containers housing the batteries and inverters are lifted into place on top of shallow concrete pads, and everything is connected together before final testing.

ENERGY HUBS

Designing Energy Hubs to ensure safety and minimise neighbourhood impact

Project sites are carefully chosen based on existing visual screening from roads, footpaths, houses and elevated viewpoints. This might be existing trees, hedgerows, other buildings, or natural features like slopes and ridges. Additional planting typically results in a minimum ten metre wide channel of shrub and tree planting around a site making it  practically invisible to local residents and walkers. Noise assessments are carried out for all sites and, in built-up areas, planting may be supplemented by an acoustic fence to contain noise within the site.

All Clearstone projects must comply with the standards set out in our comprehensive Battery Safety Management Plan. These standards cover all aspects of the project – technology, site design, installation, operation and emergency response plan – to ensure that it meets the highest safety levels.

Each battery container is designed with several layers of operational monitoring and fire prevention systems to ensure safe operation across the project lifetime. These safety systems undergo hundreds of hours of rigorous testing to ensure that they work as they are designed to. 

 

Prioritising sustainability and the environment

We treat each one of our projects as an opportunity to increase biodiversity and strengthen natural ecosystems. To deliver on this commitment up to half of the project site is set aside for dedicated ecological enhancements. While sustainable practices minimise emissions and materials wastage across the project lifespan.

  • Use of concrete on site is minimised with access roads and paths constructed from permeable materials to encourage drainage
  • Wildflower and grass planting between the battery containers encourages insects and pollinators
  • Using native trees and shrubs to construct site boundaries creates new wildlife habitats
  • Dedicated wildlife enhancement areas within the project site usually include ponds, bat and bird boxes, butterfly banks and log pile housing

Each of our projects delivers a minimum 20 per cent increase in biodiversity. Where possible, all construction and battery materials are recycled at the end of their operational lifetime or the end of the project.

Anatomy of a battery project

Discover the key components of a battery energy storage project

Substation switchgear
Perimeter fence
Battery cell container
CCTV towers
Inverter

Convert current from DC to AC

Hedgerow Screening
Transformer

Increases the voltage to meet the required voltage at the local network

Maintenance road

Projects

DARTFORD Energy Hub – 300MW battery energy storage project

Warley Energy Hub Public Consultation

Read more

warley Energy Hub – 200MW battery energy storage project

Warley Energy Hub Public Consultation

Read more

BRAMFORD Energy Hub – 400MW battery energy storage project

Bramford Energy Hub Public Consultation

Read more

Clearstone Energy – great oak Energy Hub

Public Consultation Brochure

Read more

WilloWS GREEN SOLAR FARM – CABLE ROUTE proposal

Detailed project overview

Read more

Axminster Energy Hub Public Consultation

Axminster Energy Hub is a significant energy infrastructure project that will modernise the local electricity grid to support the transition […]

Read more

Worset Lane Energy Hub- 200MW battery energy storage project

Worset Lane is a large scale battery energy storage project that will be built on land adjacent to National Grid’s Hartmoor 275 kV high voltage substation near Hartlepool.

Read more

Junction 27 Energy Hub – 400MW battery energy storage project

Clearstone Energy has secured a grid connection at Tiverton for a battery energy storage project. We are in the process of sharing our proposal with the local community for their input.

Read more

Warley Energy hub – 57 MW battery energy storage project

The Warley Battery Energy Storage  project is located at Upminster on the outskirts of East London. The project is on National Grid land adjacent to its 275kV Warley substation.

Read more